Stacks These stacks had to be installed in the same day. |
|
Complete
with three guy wires each, these stacks (30" diameter) had to be
hoisted into position near many electric lines that were so close that
we had them turned off during the day. This left our customers's plant
completely without electricity, so we had to finish both stacks in one
day.
|
![]() |